How Long Does Metal Building Installation Take?

how long does a metal building installation take?

Most standard metal buildings are installed on-site in as little as one to two days, provided the permits are already approved and the foundation is in place. Larger or more complex steel buildings can take up to three to four weeks for completion. In some instances, the answer depends on the entire metal building design and construction process because every step contributes to the entire project timeline.

Join our metal building installation team from Eagle Carports as we map out the construction process and the key factors that lead to metal building installation timelines. We want our customers to have a general idea of what to expect beforehand, so you can prepare your property for timely installation.

Installation Process and Timeline for Metal Buildings

Metal building installation follows a predictable, start-to-finish sequence that moves from design approvals and scheduling to delivery, on-site assembly, and final inspection. Your specific project's actual pace depends on building size, design complexity, weather, and local codes—but understanding the flow helps you plan the project timeline with confidence.

Planning and Design Phase

The planning phase is where your pre engineered metal building takes shape—choosing and finalizing size, loads, openings, and customization options to match use and site conditions. We align drawings with local building codes and, when required, complete structural engineering so permitting and manufacturing start smoothly.

Timeline: 1–2 days for standard; up to 2 weeks for custom builds that may require additional drawings and extra engineering.

Obtaining Permits and Code Check

Local building codes determine wind/snow loads, setbacks, inspections, and submittal requirements—sometimes including stamped drawings. We coordinate documents so your application moves cleanly through review and you can schedule manufacturing with minimal delays.

Timeline: 1–4+ weeks, jurisdiction-dependent.

Site Preparation

Site prep ensures a level, compacted site with clear access for the crew and equipment. If using a concrete slab, allow it to cure properly per your contractor’s guidance before construction begins.

Timeline: 1–5 days, project-specific. Gravel and dirt can be completed in a single day for smaller projects.

Manufacturing and Scheduling

With approvals in place, we release steel components to production and lock delivery dates that align with your on-site schedule. Lead times vary by options and season.

Timeline: 1–3+ weeks, option- and season-dependent.

Delivery and On-Site Staging

Materials are unloaded, inventoried, and staged for efficient lifts and safe movement around the site. Good access and staging space, as well as having all your permits in place and a compliant concrete foundation completed before our arrival, help keep the installation sequence smooth.

Timeline: A few hours to 1 day.

Frame Erection

Primary frames are set and squared, followed by secondary members to establish the building’s skeleton. Pace is influenced by crew experience, weather conditions, and site logistics.

Timeline: Just a few hours for carports; between one and a few weeks for a medium-sized commercial metal building.

Panels, Trim, Doors, and Windows

Installing the roof and wall panels, closures, trim, roll-up or walk through doors, and other custom components will add to the timeline. This phase locks in weather protection and contributes to overall structural integrity.

Timeline: 1 day.

Utilities and Interior Finishing

Electrical and plumbing work, HVAC, and any interior partitions or finishes proceed after the shell is complete. Scope and complexity determine duration, especially for specialty equipment or inspections.

Timeline: Varies—typically a few days to a week.

Walkthrough and Final Inspection

A quality review to confirm structure details and prepare for any required local inspections. Once approved, your building is completed and ready for use.

Timeline: Same day.

Factors That Determine Steel Building Installation Timelines

Every steel building project is unique, with several factors influencing the overall project timeline for installation.

Larger steel building structures need more components and connections. Bigger spans or tall eave heights add time on site.

Lean-tos, mezzanines, canopies, or cranes turn simple installs into complex buildings. More detail means more process steps.

Local codes, obtaining permits, and structural engineering requirements can extend the project timeline before crews mobilize.

Extreme weather like high winds, rain, snow, or heat can slow work or pause lifts. Weather is the most common wildcard in a construction timeline.

Tight access, soft ground, or limited staging area add time. Good logistics at the construction site reduce delays.

Custom colors, special doors, or unique steel components may require extra manufacturing time. Early decisions keep construction moving.

A larger, well-coordinated construction team can complete an installation faster with the same quality standards.

If a concrete foundation is used, confirm the slab is within tolerance and cured before you schedule the installation of your metal building.

Electrical and plumbing work, insulation, and interior systems add to the overall timeline after the shell of a prefabricated metal building is up.

How Long Does It Take to Install Different Types of Metal Buildings

Timeline ranges below focus on on-site installation for pre engineered metal buildings once approvals are in place and the site is ready.

Metal Carports and Metal RV Covers

Metal carports and metal RV covers are often installed in a few days because the structures are open, use fewer steel components, and require minimal anchoring compared to enclosed buildings. Height, width, and ground conditions can add time—taller legs, uneven sites, or high-wind/snow load requirements may require extra bracing and more anchors, but most pre engineered metal carports in this category go up quickly.

how long does a metal carport or RV cover installation take?
how long does a metal garage installation take?

Metal Garages

Plan on roughly one to two weeks for standard sized metal garages with roll-up doors, walk doors, and windows. Enclosing walls adds panel, trim, and flashing steps, and aligning multiple openings takes careful layout to maintain structural integrity. Adding insulation, heavier doors, or custom accessories extend steel building construction times slightly.

Agricultural Steel Buildings

Installing a steel agricultural building can range from a few days for small metal barns to about three weeks for larger spans or multi-bay designs. Farm structures frequently include wide, clear openings for equipment, ridge vents or cupolas, and specialized doors—which all adds coordination and fastening time.

how long does a metal barn installation take?
how long does a metal commercial building installation take?

Commercial Steel Buildings

Metal commercial buildings can take up to two weeks to several months to install, depending on building complexity, interior build-out, and inspections. Commercial steel building projects often involve more trades (electrical and plumbing work by others, HVAC, fire/life-safety, etc), stricter local building codes, and staged deliveries. Coordination among crews and required approvals drive the longer construction timeline for these more complex steel structures.

Benefits of Working With Our Metal Building Experts

Choosing Eagle Carports as your source for high-quality metal buildings means your project benefits from proven process control and reliable scheduling.

Some of the benefits of working with our team include:

  • Seamless delivery and installation process coordinated to your project timeline
  • Clear communication on dates, requirements, and what happens on site each day
  • Experienced contractors and crew focused on safety and structural integrity
  • Guidance on local regulations, local codes, and documentation requirements
  • Nationwide logistics that help maintain minimal delays despite weather or access limits
  • Pre engineered product lines that speed steel building installation without sacrificing quality
  • Options for doors, windows, and accessories to match your metal building customization options
  • Post-installation support so you know what to expect after construction

Contact Our Metal Building Installation Team Today

At Eagle Carports, we design, deliver, and install your metal building with ease. Use our online design customization tool to chose the perfect size, colors, doors, and options, see real-time pricing, and request your preferred delivery window. Once approved, we schedule manufacturing, coordinate seamless delivery, and our crew completes installation on site.

Contact us for support or to learn more by calling  800-579-8589 or filling out our contact form below to get started.